SMBC’s El-Rakshy: Speed to grid decides Australian BESS winners

Potentially significant opportunities await battery energy storage systems (BESS) that are able to come online in 18 months to two years and plug into Australia’s energy grid, a senior official at Sumitomo Mitsui Banking Corporation told Infralogic.

While BESS operators are currently battling plummeting daily trading profits, SMBC’s MD and Head of Structured Finance for Australia, Tarek El-Rakshy warns that a massive supply shock is looming.

As major coal plants approach their retirement dates, there is a lag between the investment required and replacement capacity coming online. This could create “huge arbitrage opportunities” for connected battery assets entering the grid in around 18 months to two years from now, he said.

“Between now and then, there is basically a lag between an investment that should be happening and the retirement of these assets. And if the government doesn’t fix this issue, we’re going to have a major problem,” he said.

Data from the Australian Energy Market Operator shows that the queue of generation and storage projects waiting to connect to the National Electricity Market has ballooned to 80.9 GW, surpassing the grid’s total existing installed capacity of 77 GW.

Even though the investment interest is huge, 88% of the total pipeline is in the early application and proponent implementation stages due to commercial and regulatory complexities, AEMO says in the report. According to its Connections Scorecard, one-third of all projects have been sitting in the queue for over two years without moving forward.

With cheap baseload power still circulating, utilities see less urgency to lock into expensive long-term contracts, El-Rakshy said. Faced with suppressed power prices on one side and soaring local construction costs on the other, many green energy developers are choosing to postpone their builds, putting the broader investment thesis into a temporary holding pattern, he added.

SMBC, which has deployed about 30% of its AUD 13bn loan book into Australian renewables, views the timing of BESS projects as key to their profitability.

“If you have a battery storage portfolio right now relying primarily on merchant risk, you’re going to be in trouble,” El-Rakshy said.

“If you have been more considered in your views and you’ve got the majority of your long-term contracts, and that will bridge you through the next 18 months to two years, you’re fine. If you’ve just built the portfolio and you’re about to hit the market, you could face more challenging market conditions. If you’re about to invest now and that will come online in two years’ time, you’re probably going to be okay,” he said.

Bring your own new clean energy (BYONCE)

With a structured finance team of 30 staff in Australia, SMBC, which regularly ranks among the top mandated lead arrangers for project finance in Infralogic’s League Tables, also sees digital infrastructure as currently a large growth area.

Australia’s status as a Five Eyes alliance partner and its geopolitical safety have helped attract investment into the segment, said El-Rakshy.

Five Eyes members are typically granted “excepted foreign state” status, allowing cross-border capital, pension funds, and co-investments to flow smoothly between the US and member countries. Being a “trusted Five Eyes member” positions the country as a secure regional hub to attract large-scale data center and AI training investments, the Australian Department of the Prime Minister and Cabinet wrote in a consultation paper this September.

The other four members countries are New Zealand, Canada, United States, and the UK.

Australia’s seemingly abundant availability of natural resources has also helped draw investors, said El-Rakshy.

“Similar to the BESS story, it is an arbitrage play. Supply and demand fundamentals at the moment mean that if you’re the quickest to market on a data centre or digital infrastructure play, you will do very well because the supply-demand dictates that,” he said.

A joint industry and economic study published in August by Data Centres Australia and Mandala states that “demand from consumers and businesses adopting cloud and AI tools is absorbing capacity as fast as it comes to market. Vacancy rates are low and pre-leasing of capacity under construction remains elevated, reflecting genuine domestic need for compute services rather than speculative development.”

However, social licenses – or community acceptance – has emerged as a big bottleneck for new developments “and the saying is – and this is very cheesy but I love it and it came out of the US – you can’t build a data centre without BYONCE (bring your own new clean energy),” El-Rakshy said.

Impending full binding legislation – scheduled for rollout in early 2027 – mandating data centres to underwrite their own clean power supply basically means that “the data centre developers have to have a marriage of convenience with energy developers and ultimately find solutions that allow them to demonstrate that they are responsible in their energy utilization,” he said.

This is going to be challenging as even a large data centre can be built in two years, but a wind or solar project can take up to three or four years, he added.

“How are you going to manage that balance to allow this BYONCE to be there when you start your project? I just think there are some fundamental issues in the market,” he said, adding that the micro challenges are around social licensing and its implications on project revenue.

Flight to quality

Despite the challenges to the two high-growth areas of renewables and digital infrastructure in the country, there’s no better flight to quality than Australia among global markets, said El-Rakshy, who started out as a field engineer at Halliburton in the North Sea, while based in the United Arab Emirates between 1998 and 2000.

He then returned to the UK, where he is originally from and designed bridges for a couple of years before moving to Australia for a business degree, subsequently transitioning into banking.

While some Asian banks are reassessing their global deployment strategies amid geopolitical uncertainty, Australia’s flight-to-quality characteristics are helping to attract capital, El-Rakshy said.

Now approaching his 20th year with SMBC, he points to the bank’s heft as a global project finance house to get deals over the line.

“We’re taking accountability for the risk that we’ve structured and the risk that we’re syndicating in the market,” he said.

“We’re comfortable enough that when we sit in front of a new bank coming in and they look at it from a first principle risk perspective, we’re able to justify the structures that have been put in place and why it’s appropriate for them to consider that structure and potentially come in,” he added.

With the influx of cross-border institutional capital, there is a role for banks like SMBC to structure deals and appropriately allocate and manage risks, he said, adding that risk-conscious Asian banks are able to derive comfort from their presence.

He also pointed to Australia’s stable political environment, the availability of large transactions, deal pipelines, certainty of execution, and finite timelines as factors attracting US and European sponsors, as well as multiple sovereign wealth funds.